A. PREPARATORY ACTIONS |
ACTIVITY STATUS |
|
A1 Self-assessment, stakeholder mapping and development of work plan |
Completed
|
|
A2 Elaboration of procurement specifications and implementation of procurement
procedures for external services (Saulkrasti Municipality procurement procedures) |
Completed |
|
A3 Elaboration of communication strategy |
Completed |
|
A4 Elaboration of project impact monitoring guidelines |
Completed |
|
A5 Mapping of ecosystems and their services |
Completed |
B. IMPLEMENTATION ACTIONS
|
|
|
B1 Economic valuation of ecosystems and their services for Pilot Implementation Areas |
Completed |
|
B2 Elaboration and economic evaluation of the development scenarios for Pilot
Implementation Areas |
Completed |
|
B3 Incorporation of the results of the evaluation of scenarios in the municipal Spatial
Development Plans/Nature Conservation Plans |
Completed |
|
B4 Risk prevention for preservation of the conservation status and values of the ecosystems
(Nature Design Park development) |
Completed |
|
B5 Development of strategic recommendations for Latvia |
Completed |
C. MONITORING OF THE IMPACT OF THE PROJECT ACTIONS
|
|
|
C1 Monitoring of the impact of the project activities |
Completed |
|
C2 Monitoring of the socio-economic impact of the project activities |
Completed |
D. COMMUNICATION AND DISSEMINATION ACTIONS
|
|
|
D1 Web page |
Completed |
|
D2 Public information and education materials (leaflets, brochures, newsletters, short films, publications) |
Completed |
|
D3 Public information and education events
(seminars, common work events, events for universities, schools, nature education events) |
Completed |
|
D4 Experience exchange and networking |
Completed |
|
D5 Layman’s Report |
Completed |
E. PROJECT MANAGEMENT AND MONITORING OF THE PROJECT PROGRESS
|
|
|
E1 Project management |
Completed |
|
E2 Audit |
Completed |
|
E3 After-Life Communication plan |
Completed |